Another project "Made by EEPro" goes online in South Africa

26.04.2018

The second project in the Kruger National Park, with a system power of 844,8 kWp and in sight of the largest camp in the National Park, has also been successfully put into operation on the internal network of SANParks after a...... Read more

EEPro’s third PV plant in southern Africa.

05.09.2017

In the Kruger National Park, after a construction period of about 8 weeks, the Lower Sabie Rest Camp project (537,6 kWp) was successfully connected to the internal 6.6kV network of SANParks and put into operation. The first out...... Read more

Commissioning of the solar carport system Airport Weeze

01.09.2016

On the local Airport Weeze we built a photovoltaic carport system with a power of 4 MWp. The construction phase took only 6 weeks, the carports have space for approx. 1500 vehicles. Because of the short timeline...... Read more

EEPro goes Dubai

25.04.2016

In the first half of 2016, EEPro builds together with our project partners Eliotec L.L.C., Dubai, our first PV-System in the United Arab Emirates. This project will be realized within the scope of the Sheikh Zayed housing...... Read more

Commissioning of Solarpark Waschow

30.06.2015

The solar park Waschow is located on the railway line Hagenow Land - Bad Oldesloe and is equipped with a decentralized inverter solution. With a total capacity of 3.1 MWpeak this will feed-in from the beginning of...... Read more